Evonik Stockhausen GmbH

Addition of storeys and reconstruction of production area P7

Client: Evonik Stockhausen GmbH

Costumer: Evonik Stockhausen GmbH

To expand the production in an existing building it was necessary to add an 11m storey to the existing 12.0m (total of 23m). The existing building is from the 1940s. During the whole construction phase the production was not to be interrupted. Therefore the addition was built on top first and then the existing roof was removed. The construction costs add up to approximately 1.1 m Euros.

Our performances:
• Building application
• Static calculations
• Detailed and approved final design
• Steel construction drawings
• Structure planning incl. formwork and reinforcement drawings

as PDF-Document…

 